File: RELEASE-PROCESS

package info (click to toggle)
dia 0.94.0-7sarge3
  • links: PTS
  • area: main
  • in suites: sarge
  • size: 27,804 kB
  • ctags: 11,124
  • sloc: ansic: 110,979; sh: 8,442; xml: 2,988; makefile: 2,431; python: 1,789; cpp: 1,652
file content (119 lines) | stat: -rw-r--r-- 5,031 bytes parent folder | download
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100
101
102
103
104
105
106
107
108
109
110
111
112
113
114
115
116
117
118
119
Status
------

This document, at this point, is a proposal only. It attempts to
document how we intend to make the upcoming releases, in order to make
as sure as possible no stupid bugs creep in just before the release.

Contents
--------

When a new version is about to be released:

0) Day Zero (D+0): The core developers announce their intention of
   making a new release. They call for a feature freeze on the CVS
   HEAD (bug fixes are okay to commit). They also announce the
   provisional duration of the freeze before the first release
   candidate tarball is about to be made (actual freeze duration may vary for
   instance according to the perceived amount of changes since the
   last release; for the purpose of this document, it's assumed to be
   three days).

   Advanced users are encouraged to download the CVS HEAD or the
   snapshot tarballs, and pound on them.

   Make sure to check for open Bugzilla bugs with the PATCH keyword.

1) The core developers agree on the next version number. It's called
   $VERSION thereafter. They also look if DIA_PLUGIN_API_VERSION needs
   to be updated.

2) D+3: a release candidate tarball is made. It is called
   $VERSION-pre1. Simultaneously, a CVS branch is made with the name
   "DIA_$VERSION_RELEASE" (with the non-alphanumeric characters in $VERSION
   replaced by underscores, e.g. cvs tag -b DIA_0_93_RELEASE).
   $VERSION-pre1 is registered with the Bugzilla, however it is encouraged
   that bug reports are made directly (or simultaneously) to the mailing
   list.

   Please see the section below on how to make a tarball (yes, please do).

   Translators, as pulled from the Translation-Team: field in the .po
   files, are notified of the upcoming release to give them time to
   translate new strings.  No further changes to translatable strings
   should happen from now till the final release ("string freeze").
   Also mail gnome-i18n@gnome.org to notify the Gnome Translation Project
   (and perhaps get new translators).

3a) if a release-critical bug happens before D+10 (say, at D+n), the
   release process is paused until the bug is fixed and a new release
   candidate tarball $VERSION-pre2 is re-made. Go to either step 3a or
   3b with D+10 replaced by D+n+10.  Any bugs fixed that way, as well as
   further translations, must be transferred back into the main trunk
   (cvs update -j).

3b) D+10: if there are no release-critical bugs in the pre-release,
   then the same source (fetched from the CVS branch) is rebuilt with the
   final $VERSION number (and the resulting "new" version is re-tagged
   in CVS). $VERSION is registered with the Bugzilla, and all
   $VERSION-preX are removed (from now on, bugs against -preX are
   rejected as INVALID).

4) once the new release is complete and uploaded, announcements on
   freshmeat, the dia web site, the dia mailing list,
   gnome-announce-list@gnome.org, gnomefiles.org and maybe a gnotices story
   (news.gnome.org) are made.  Alerting the package maintainers for the
   various distributions is also a good idea, get names from MAINTAINERS
   and update those who have changed.

5) the CVS HEAD freeze is lifted one week /after/ the release is
   generally available, unless a release critical bug is discovered in
   the release. If the latter is the case, a new, fixed "brown bag" release is
   released and announced as soon as possible (extending the one-week
   delay on the CVS HEAD thaw).

   Once the head is lifted, the release branch is considered dead and
   should no longer be used.

How to make a tarball
---------------------
  1. make sure you have up to date build tools installed on the system.
      Libtool is an important one, as new releases add support for new
     platforms.
  2. make sure "make distcheck" runs to completion.  With automake >=
     1.5, the checks also make sure "make uninstall" removes all files 
     that got installed.
  3. check to see if the tarball builds in normal and --enable-gnome
     modes (this task should disapear with the move to 2.0; there is no
     reason to have separate dialog and menu code).
  4. Upload to ftp.gnome.org.  This is basically just scp'ing the
     tarball to widget.gnome.org, then running a command like
     "install-module dia-0.90.tar.gz", which will create bz2
     tarballs, diffs to the previous version, and signal the ftp mirrors
     (currently just ftp.gnome.org and planetmirror.com) to synchronise. 

Issues to solve
---------------

agreeing on how to properly handle the case of having only ten two-decimal
place version numbers until we hit 1.0 

How do we notify people that a) a prerelease branch is where translation
goes and b) the prerelease branch is dead when it is.

Files
-----

These files need to be updated at every release:

config.h.win32
NEWS
configure.in
doc/{en,pl}/dia.xml
dia.spec (note that the preN should go in release, not ver).

Webpages
--------

Remember to also update the webpages.  In particular, the download page,
the NEWS page and the FAQ needs updating.