1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103 104 105 106 107 108 109 110 111 112 113 114 115 116 117 118
|
project test "Complete Test Case" "1.0" 2005-10-19 2006-05-18 {
now 2005-11-19
}
resource tux "Tux"
resource tux2 "Tux2"
task m1 "Milestone Task" {
task m2 "M2" {
start 2005-10-19
}
task m3 "M3" {
task m4 "M4" {
start 2005-10-22
}
}
task m5 "M5" {
start 2005-12-01
}
task m6 "M6" {
task m7 "M7" {
start 2005-12-24
}
}
}
task e1x "Effort Task with compl. reports" {
task e2 "E2" {
start 2005-10-19
effort 2d
allocate tux2
}
task e3 "E3" {
task e4 "E4" {
start 2005-10-19
effort 2d
allocate tux2
}
task e5 "E5" {
start 2005-10-19
effort 2d
allocate tux2
complete 90
}
}
task e6 "E6" {
start 2005-12-24
effort 2d
allocate tux2
}
task e7 "E7" {
start 2005-11-17
effort 8d
allocate tux2
}
task e8 "E8" {
task e9 "E9" {
start 2005-11-07
length 3d
allocate tux2
}
task e10 "E10" {
start 2005-12-05
length 3d
allocate tux2
}
}
}
task e1 "Effort Task" {
task e2 "E2" {
start 2005-10-19
effort 2d
allocate tux
}
task e3 "E3" {
task e4 "E4" {
start 2005-10-19
effort 2d
allocate tux
}
task e5 "E5" {
start 2005-10-19
effort 2d
allocate tux
}
}
task e6 "E6" {
start 2005-12-24
effort 2d
allocate tux
}
task e7 "E7" {
start 2005-11-17
effort 8d
allocate tux
}
task e8 "E8" {
task e9 "E9" {
start 2005-11-07
length 3d
allocate tux
}
task e10 "E10" {
start 2005-12-05
length 3d
allocate tux
}
}
}
taskreport "Tasks" {
columns no, name, start, end, effort, completed, status, chart
loadunit days
}
htmltaskreport "." {
columns no, name, start, end, effort, completed, status
loadunit days
}
|