File: ICalReport.tjp

package info (click to toggle)
taskjuggler 2.3.0-1
  • links: PTS
  • area: main
  • in suites: etch, etch-m68k
  • size: 8,764 kB
  • ctags: 3,700
  • sloc: cpp: 36,852; sh: 12,761; xml: 5,541; perl: 5,207; makefile: 269; python: 258; lisp: 67
file content (35 lines) | stat: -rw-r--r-- 630 bytes parent folder | download
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
project prj "ICal Export Demo" "1.0" 2005-06-06 2005-06-26
  
resource tux "Tux"
resource tuxia "Tuxia"

task items "Project breakdown" {
  start 2005-06-06

  task plan "Plan work" {
    task phase1 "Phase 1" {
      effort 5d
      allocate tuxia
    }
    task phase2 "Phase 2" {
      effort 2d
      allocate tux
    }
  }

  task implementation "Implement work" {
    effort 5d
    allocate tux
    depends !plan
  }

  task acceptance "Customer acceptance" {
    duration 5d
    depends !implementation
  }
}

icalreport "Tux-TODO-List.ics" {
  # Only export tasks that tux is assigned to
  hidetask ~isDutyOf(tux, plan)
}