1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103 104 105 106 107 108 109 110 111 112 113 114 115 116 117 118 119 120 121 122 123 124 125 126 127 128 129 130 131 132 133 134 135 136 137 138 139 140 141 142 143 144 145 146 147 148 149 150 151 152 153 154 155 156 157 158 159 160 161 162 163 164 165 166 167 168 169 170 171 172 173 174 175 176 177 178 179 180 181 182 183 184 185 186 187 188 189 190 191 192 193 194 195 196 197 198 199 200 201 202 203 204 205 206 207 208 209 210 211 212 213 214 215 216 217 218 219 220 221 222 223 224 225 226 227 228 229 230 231 232 233 234 235 236 237 238 239 240 241 242 243 244 245 246 247 248 249 250 251 252 253 254 255 256 257 258 259 260 261 262 263 264 265 266 267 268 269 270 271 272 273 274 275 276 277 278 279 280 281 282 283 284 285 286 287 288 289 290 291 292 293 294 295 296 297 298 299 300 301 302 303 304 305 306 307 308 309 310 311 312 313 314 315 316 317 318 319 320 321 322 323 324 325 326 327 328 329 330 331 332 333 334 335 336 337 338
|
/*
* This file contains a project skeleton. It is part of the
* TaskJuggler project management tool. You can use this as a basis to
* start your own project file.
*/
project your_project_id "Your Project Title" 2011-11-11-0:00--0500 +4m {
# Set the default time zone for the project. If not specified, UTC
# is used.
timezone "America/New_York"
# Hide the clock time. Only show the date.
timeformat "%Y-%m-%d"
# Use US format for numbers
numberformat "-" "" "," "." 1
# Use US financial format for currency values. Don't show cents.
currencyformat "(" ")" "," "." 0
# Pick a day during the project that will be reported as 'today' in
# the project reports. If not specified, the current day will be
# used, but this will likely be outside of the project range, so it
# can't be seen in the reports.
now 2011-12-24
# The currency for all money values is the Euro.
currency "USD"
# You can define multiple scenarios here if you need them.
#scenario plan "Plan" {
# scenario actual "Actual"
#}
# You can define your own attributes for tasks and resources. This
# is handy to capture additional information about the project that
# is not directly impacting the project schedule, but which you like to
# keep in one place.
#extend task {
# reference spec "Link to Wiki page"
#}
#extend resource {
# text Phone "Phone"
#}
}
copyright "Claim your rights here"
# If you have any text block that you need multiple times to describe
# your project, you should define a macro for it. Macros can even have
# variable segments that you can set upon calling the macro.
#
# macro Task [
# task "A ${1} task" {
# }
# ]
#
# Can be called as
# ${Task "big"}
# to generate
# task "A big task" {
# }
# You can attach flags to accounts, resources and tasks. These can be
# used to filter out subsets of them during reporting.
flags important, hidden
# If you want to do budget planning for your project, you need to
# define some accounts.
account cost "Project Cost" {
account dev "Development"
account doc "Documentation"
}
account rev "Customer Payments"
# The Profit & Loss analysis should be rev - cost accounts.
balance cost rev
# Define your public holidays here.
vacation "New Year's Day" 2012-01-02
vacation "Birthday of Martin Luther King, Jr." 2012-01-16
vacation "Washington's Birthday" 2012-02-20
vacation "Memorial Day" 2012-05-28
vacation "Independence Day" 2012-07-04
vacation "Labor Day" 2012-09-03
vacation "Columbus Day" 2012-10-08
vacation "Veterans Day" 2012-11-12
vacation "Thanksgiving Day" 2012-11-22
vacation "Christmas Day" 2012-12-25
# The daily default rate of all resources. This can be overridden for each
# resource. We specify this so we can do a good calculation of
# the costs of the project.
rate 400.0
# This is a set of example resources.
resource r1 "Resource 1"
resource t1 "Team 1" {
managers r1
resource r2 "Resource 2"
resource r3 "Resource 3"
}
# This is a resource that does not do any work.
resource s1 "System 1" {
efficiency 0.0
rate 600.0
}
task project "Project" {
task wp1 "Workpackage 1" {
task t1 "Task 1"
task t2 "Task 2"
}
task wp2 "Work package 2" {
depends !wp1
task t1 "Task 1"
task t2 "Task 2"
}
task deliveries "Deliveries" {
task "Item 1" {
depends !!wp1
}
task "Item 2" {
depends !!wp2
}
}
}
# Now the project has been specified completely. Stopping here would
# result in a valid TaskJuggler file that could be processed and
# scheduled. Here reports will be generated to visualize the
# results.
navigator navbar {
hidereport 0
}
macro TaskTip [
tooltip istask() -8<-
'''Start: ''' <-query attribute='start'->
'''End: ''' <-query attribute='end'->
----
'''Resources:'''
<-query attribute='resources'->
----
'''Precursors: '''
<-query attribute='precursors'->
----
'''Followers: '''
<-query attribute='followers'->
->8-
]
textreport frame "" {
header -8<-
== TaskJuggler Project Template ==
<[navigator id="navbar"]>
->8-
footer "----"
textreport index "Overview" {
formats html
center '<[report id="overview"]>'
}
textreport "Status" {
formats html
center -8<-
<[report id="status.dashboard"]>
----
<[report id="status.completed"]>
----
<[report id="status.ongoing"]>
----
<[report id="status.future"]>
->8-
}
textreport wps "Work packages" {
textreport wp1 "Work package 1" {
formats html
center '<[report id="wp1"]>'
}
textreport wp2 "Work package 2" {
formats html
center '<[report id="wp2"]>'
}
}
textreport "Deliveries" {
formats html
center '<[report id="deliveries"]>'
}
textreport "ContactList" {
formats html
title "Contact List"
center '<[report id="contactList"]>'
}
textreport "ResourceGraph" {
formats html
title "Resource Graph"
center '<[report id="resourceGraph"]>'
}
}
# A traditional Gantt chart with a project overview.
taskreport overview "" {
header -8<-
=== Project Overview ===
The project is structured into 2 work packages.
# Specification
# <-reportlink id='frame.wps.wp1'->
# <-reportlink id='frame.wps.wp2'->
# Testing
=== Original Project Plan ===
->8-
columns bsi { title 'WBS' },
name, start, end, effort, cost,
revenue, chart { ${TaskTip} }
# For this report we like to have the abbreviated weekday in front
# of the date. %a is the tag for this.
timeformat "%a %Y-%m-%d"
loadunit days
hideresource 1
balance cost rev
caption 'All effort values are in man days.'
footer -8<-
=== Staffing ===
All project phases are properly staffed. See [[ResourceGraph]] for
detailed resource allocations.
=== Current Status ===
Some blurb about the current situation.
->8-
}
# Macro to set the background color of a cell according to the alert
# level of the task.
macro AlertColor [
cellcolor plan.alert = 0 "#90FF90" # green
cellcolor plan.alert = 1 "#FFFF90" # yellow
cellcolor plan.alert = 2 "#FF9090" # red
]
taskreport status "" {
columns bsi { width 50 title 'WBS' }, name { width 150 },
start { width 100 }, end { width 100 },
effort { width 100 },
alert { tooltip plan.journal
!= '' "<-query attribute='journal'->" width 150 },
status { width 150 }
taskreport dashboard "" {
headline "Project Dashboard (<-query attribute='now'->)"
columns name { title "Task" ${AlertColor} width 200},
resources { width 200 ${AlertColor}
listtype bullets
listitem "<-query attribute='name'->"
start ${projectstart} end ${projectend} },
alerttrend { title "Trend" ${AlertColor} width 50 },
journal { width 350 ${AlertColor} }
journalmode status_up
journalattributes headline, author, date, summary, details
hidetask ~hasalert(0)
sorttasks alert.down, plan.end.up
period %{${now} - 1w} +1w
}
taskreport completed "" {
headline "Already completed tasks"
hidetask ~(plan.end <= ${now})
}
taskreport ongoing "" {
headline "Ongoing tasks"
hidetask ~((plan.start <= ${now}) & (plan.end > ${now}))
}
taskreport future "" {
headline "Future tasks"
hidetask ~(plan.start > ${now})
}
}
# A list of tasks showing the resources assigned to each task.
taskreport wp1 "" {
headline "Work package 1 - Resource Allocation Report"
columns bsi { title 'WBS' }, name, start, end, effort { title "Work" },
duration, chart { ${TaskTip} scale day width 500 }
timeformat "%Y-%m-%d"
hideresource ~(isleaf() & isleaf_())
sortresources name.up
taskroot project.wp1
}
# A list of tasks showing the resources assigned to each task.
taskreport wp2 "" {
headline "Work package 2 - Resource Allocation Report"
columns bsi { title 'WBS' }, name, start, end, effort { title "Work" },
duration, chart { ${TaskTip} scale day width 500 }
timeformat "%Y-%m-%d"
hideresource ~(isleaf() & isleaf_())
sortresources name.up
taskroot project.wp2
}
# A list of all tasks with the percentage completed for each task
taskreport deliveries "" {
headline "Project Deliverables"
columns bsi { title 'WBS' }, name, start, end, note { width 150 }, complete,
chart { ${TaskTip} }
taskroot project.deliveries
hideresource 1
}
# A list of all employees with their contact details.
resourcereport contactList "" {
headline "Contact list and duty plan"
columns name,
email { celltext 1 "[mailto:<-email-> <-email->]" },
managers { title "Manager" },
chart { scale day }
hideresource ~isleaf()
sortresources name.up
hidetask 1
}
# A graph showing resource allocation. It identifies whether each
# resource is under- or over-allocated for.
resourcereport resourceGraph "" {
headline "Resource Allocation Graph"
columns no, name, effort, rate, weekly { ${TaskTip} }
loadunit shortauto
# We only like to show leaf tasks for leaf resources.
hidetask ~(isleaf() & isleaf_())
sorttasks plan.start.up
}
|