project "Taskroot Example" 2005-07-22 - 2005-08-26 {
timezone "America/Denver"
}
task items "Project breakdown" {
start 2005-07-22
task plan "Plan work" {
length 3d
}
task implementation "Implement work" {
task phase1 "Phase 1" {
length 5d
depends !!plan
}
task phase2 "Phase 2" {
length 3d
depends !phase1
}
task phase3 "Phase 3" {
length 4d
depends !phase2
}
}
task acceptance "Customer acceptance" {
duration 5d
depends !implementation
}
}
taskreport tasks "My Tasks" {
formats html
taskroot items.implementation
}
|